The work you did not plan for still turns up.

Two teams of four. The same work at the same pace, the same urgent requests arriving at the same moments. One plans to three quarters of its capacity. The other plans to all of it.

3 times a fortnight
75% of capacity

Nobody is idle in either team. Every figure on the screen is working every day; the only difference is what they are working on when the urgent request arrives.

Day 0 Delivery Doctor

What the model assumes

Both teams are four people working at the same pace on the same kind of work, and both take urgent requests immediately. Nothing here says that a busy team is a slow team. Four costs are charged, and you can check each one against your own team.

Work is lumpy. A committed item is one to five person-days. Every ten days the team commits to enough of them to fill its share of the next ten days, and what it commits to is expected by the end of those ten days. A cycle's worth of lumpy items rarely packs neatly into the days available, and whatever does not fit runs past its date.

Urgent work is never refused. It goes to whoever is cheapest to interrupt: someone free, then someone on debt or learning work, and only then someone holding committed work. An urgent request is half a day to two days of work. Whoever takes it parks what they were doing, and picking that up again costs about a fifth of a day. Which of the three happens is most of the difference between these two teams.

Debt and learning are pulled last. A piece is one to three person-days, and it is picked up only when nothing committed is waiting. It is put down again the moment something is.

Carrying work forward counts against the next commitment. The fuller plan is never allowed to commit a fresh full load on top of what it is already carrying, which is kinder than what usually happens. Nothing in the model credits the debt and learning work with a payoff either, so the third readout is the fairest number on the page and the one that argues against holding capacity back.

Both teams start on day 0 with nothing in hand, so the readouts fill up over the first thirty days and settle after a few planning cycles. Set the second dial to 100% and the two panels become the same simulation: the readouts should agree, give or take the run. That is the check that the comparison is not rigged.